Bridge Culvert Bindi Bindi – Toodyay Road
The demolition and construction of a box culvert bridge spanning 12m
|
|
|
Project Details
- Demolition of Composite Timber/Concrete Bridge
- Construction of new RC base slabs, wing walls, culverts
- Road subbase construction, batters and two coat seal
- W beam safety barriers installed along the side of the roads
- Rock pitching around the inlets and outlets of the culverts
- Side track construction
- Creek dewatering
- Tree removal
- Complex Traffic management
- Liaising with local farmers to ensure all stakeholders were
satisfied
|
|
|
Key Information
Contract Period:
5 weeks
Client:
The Shire of Toodyay
Contract Value:
$500,000
|
|
|
|
|
|
|
|
|
|