Project Details
- Design & construction of a cofferdam consisting of
approximately 6,500M3 of clay, granite rock & sand.
- Dewatering of inside of cofferdam.
- Demolition and removal of existing jetty structure and
concrete boat ramp
- Construction of 9 concrete piles, connected into competent
granite bedrock below the sea floor.
- Fabrication and Installation of a 36.6m steel superstructure
jetty
- Supply and installation of 40 precast concrete boat ramp
panels
- Installation of FRP decking, chaffers, fenders and light pole
onto Jetty structure
- Due to the high profile location of works Neo effectively managed
relations with local stakeholders such as the local fishermen and sea
rescue.
- Removal of 6,500M3 cofferdam and rehabilitation of site before
demob
|
|
|